Part 1 - Design Phase
Began December 28, 2009 when we contracted with Bobby Castle Construction to develop the Architectural, Civil and Structural drawings needed to secure the Site Plan approval and Building Permits from the City of Austin and Travis County.
Part 2 - Construction Phase:
Our Construction Loan with CDF was closed on June 11, 2010.
Our Groundbreaking Service was conducted on Sunday June 13, 2010.
We officially broke ground in early November 2010 and took occupancy our new building on June 22, 2011...
Our first Sunday Worship in the new Ministry Center was held on June 26, 2011!